ADA (Americans with Disabilities Act) Improvement Program - 2021 (CRP 5922)
What’s Happening Engineering: We are completing the engineering for the project and are preparing to advertise for competitive bids.
Group 1
Group 2
About the Project Planned improvements for the 2021 ADA Improvement Program (CRP 5922) are intended to improve accessibility and sidewalk connectivity at various locations throughout the County, and will include the following:
Removing and reconstructing existing curb ramps and sidewalks within the project area that do not meet ADA requirements.
Adding new curb ramps and sidewalks within the project area where none exist.
These locations include:
Group 1 - Ainsworth Avenue South at 110th Street South
Group 2 - 168th Street East (Gem Heights Drive East to 171st Street Court East)
Project Timeline
May 2020 to July 2020: Complete field surveys.
July 2020 to December 2020: Complete engineering and environmental documentation.
January 2021 to March 2021: Complete construction plans, specifications, estimates.