Canyon Road East - 72nd St E to Pioneer Way E (CRP 5903)

What's Happening

Engineering: We're beginning the preliminary engineering for this project and will be reviewing the existing site conditions to help define the planned improvements.

Survey: County staff will be gathering field data of the project area.

Photo of project map.
Photo of Canyon Road East.

About the Project

Planned improvements to Canyon Road East - 72nd Street East to Pioneer Way East (CRP 5903) are intended to link road projects to the north and south for which we are currently designing and acquiring right of way. The project to the south is Canyon Road East - 84th Street East to 72nd Street East (CRP 5736), and the project to the north is Canyon Road East Northerly Extension - Pioneer Way East to 52nd Street East/62nd Avenue East (CRP 5643). The improvements currently planned for this project include:

  • Expanding to four lanes with left turn lanes as needed.
  • Adding concrete curbs, gutters and sidewalks.
  • Adding street lighting.
  • Adding an enclosed storm drain system, as well as stormwater treatment facilities.

Project Timeline

November 2019: Complete field surveys.

November 2019 to 2021: Complete preliminary engineering and environmental documentation. Final engineering, right of way acquisition, and construction are dependent on availability of funding.

Contact Us


Patrick Baughman, P.E., PMP
Design Supervisor
Phone: (253) 798-3157

Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409