122nd Avenue East (152nd St E to 145th St E) (CRP 5895) 

What's Happening


Engineering: The project is in the early stages of the preliminary engineering phase.


About the Project


Planned improvements to the 122nd Avenue East corridor from 152nd Street East to 145th Street East (CRP 5895) are intended to increase efficiency of the corridor and improve safety, and includes the following:
  • Adding a two-way left-turn lane and an additional southbound through lane.
  • Install cement concrete curb, gutter, and sidewalks.
  • Install an enclosed storm drainage system, and water quality treatment and flow control facilities.
  • Replace the existing traffic signal system.
  • Install street lighting.     

Project Timeline

June 2019 to July 2020Topographic survey work of the existing conditions, prepare preliminary construction plans, and finalize right-of-way plans.

August 2020 to September 2022Right-of-Way acquisition, environmental permitting, final engineering, and prepare construction documents.

October 2022 to August 2024: 
Construction.