2020 Asphalt Overlay Program (CRP 5885)

What's Happening


Engineering: 
We're beginning the final engineering for the project. Currently we're gathering information about the existing conditions, coordinating with utility companies, and completing the plans and specifications.

Land: All improvements are expected to fit within the existing right-of-way.

Survey: County surveyors will be in the area gathering field data of the project area.

About the Project


The project involves resurfacing the existing asphalt pavement and curb ramp upgrades to meet ADA standards at various locations throughout the County. The locations include:
Group 1: 192nd Street East (B Street East to 22nd Avenue East)
Group 2: 234th Avenue East (South Prairie Road East to Bonney Lake City Limits w/o SR 410)
Group 3: South Prairie Road East (231st Avenue East to 239th Avenue East)
Group 4: South Prairie Road East (112th Street East to 100' NW of 202nd Avenue East)
Group 5: 214th Avenue East (120th Street East to 1000' N/O South Prairie Road East)
Group 6: 85th Street East (McKinley Avenue East to Portland Avenue East)
Group 7: 122nd Avenue East (Sunrise Boulevard East to 1000' N/O Sunrise Boulevard)
Group 8: 96th Street East (SR 162 to 300' E/O SR 162)

Project Timeline

May 2019 to January 2020Gathering of field data, design engineering, development of construction plans, specifications, and estimates. 

Spring 2020: Construction begins.