Foothills Trail (South Prairie to Buckley) - Phase 2

Banner photo of mossy trail

What's Happening


Pierce County issued the Notice to Proceed for July 13, 2016. The contractor, Pivetta Brothers Construction, is on site performing the following work:
  • Placing top soil and gravel shoulders
  • Wetland plantings are scheduled for October 2017

About the Project


Planned improvements to Foothills Trail - South Prairie to Buckley
(
CSM 6164)
will tie the previously built section of the trail (Phase 1) to the existing Foothills Trail section in the City of Buckley. Improvements will include the following:
  • Adding 1.32 miles of new trail, including 0.54 miles of elevated pin pile bridge
  • Adding 0.78 miles of horse path adjacent to the trail.

Project Timeline


May 13, 2016: Pierce County awarded the contract to Pivetta Brothers

June 16, 2016: Pierce County hosted the Pre-Construction Meeting

July 13, 2016: Pierce County issued the Notice To Proceed

Fall 2017: Anticipated Substantial Completion and Physical Completion dates
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Pivetta Brothers Construction, Inc.
Contractor
Phone: (253) 862-7290
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
1812 Pease Avenue
Sumner, WA 98390